On the Kozina Bypass Project, with a total length of 1.5 km, SLOMAN d.o.o. successfully supervised the construction of three bridge structures:

➡️ a railway overpass (structure 4.1) with a length of 39.30 m over the main railway line Divača–Koper, the most important structure on the bypass
➡️ an underpass for a forest road (structure 3.1)
➡️ an underpass for a local road (structure 3.2).

🔹 The overpass is an integral post-tensioned structure, founded on piles with a massive arched design and a single span of 34 m between abutments.
🔹 The technology and construction process had to be carefully adapted to the intensive railway traffic on this section of the Divača–Koper main line.

Particularly demanding were the works that required railway line closures, as determined by the railway operator.

The project began in December 2022, and completion is expected in mid-2025.